Connect contracts, certificates and invoices
Use the same project and milestone references on site and in the ledger. Distinguish work performed, work certified and amounts eligible for billing. Reference the approved variation to keep quantities and prices on the same basis.
Example: billing and cash receipts differ
Assume planned milestone work of THB 400,000. The customer certifies and accepts billing of THB 300,000, retains THB 15,000 and pays THB 260,000. Track THB 25,000 still payable on the milestone, THB 15,000 in retention and THB 100,000 of planned work not yet certified.
See the cash needed before completion
Bring together booked costs, open purchase orders and labour or subcontracting still required. Keep costs incurred separate from commitments so they are counted once, then compare expected payment dates with customer collections.
What to consider
- Tie milestones to certification and billing
- Separate retention from currently due receivables
- Forecast cost to complete and scheduled outflows
Checklist
- Trace one milestone from contract to bank receipt
- Track retention terms and follow-up owners
- Have site teams confirm cost to complete before reviewing margin